Background

A new high-speed line for the company’s largest customer was weeks from launch — with no plan and mounting problems.

The company had purchased a new high-speed packaging machine to run a new product for its largest customer, but had no proper launch plan in place. Weeks before launch, several additional problems emerged: the line couldn’t hit its oxygen targets, bag sealing issues appeared, and key parts were missing.

No Launch Plan

Company did not have a proper plan in place for starting up the new line

Oxygen Target Shortfall

New line couldn’t hit the oxygen targets required for the product

Bag Sealing Issues

Line was experiencing bag sealing problems weeks before launch

Missing Parts

Startup was missing key parts, including a gas mixer and simplex parts

CaseStudy3BackgroundImage
CaseStudy4ActionImage1
Action

Saphineia worked through the equipment constraints one by one, then built the launch discipline that had been missing.

  • Redesigned the lance system to improve gas injection and reduce nozzle clogging.
  • Developed a backup gas solution to address insufficient plant air supply.
  • Identified and ordered missing parts, including the gas mixer and simplex parts.
  • Adjusted the bag handling process to address sealing and gas-phase issues.
  • Established daily action tracking and coordinated directly with OEMs and service providers.
  • Created bilingual SOPs in English and Spanish for the line operators.

70% vs. 50%

Actual vs. target production ramp, week 3

95% vs. 80%

Actual vs. target production ramp, week 4

Results

The line went from behind schedule to exceeding its ramp curve.

By week 3, actual production ramp reached 70% of steady state, against a 50% target. By week 4, it reached 95% of steady state, against an 80% target.

“We retained Saphineia to help us start up a new high speed packaging machine in connection with a product launch for our largest customer. Our team was crying for support and within a matter of weeks, we moved from running well behind our launch targets to well ahead. I don’t know where I would have been without Saphineia; their support was a godsend. Our people gained confidence with them here and learnings from that experience will provide ongoing dividends to our business.”

— Director of Operations, Contract Food Manufacturer

Quote

Saphineia did an excellent job recognizing common operational challenges while still appreciating what makes our business unique. People felt heard, no feedback was dismissed, and the team consistently approached problems as allies on the same side of the table.

CEO of Saphineia Client
Quote

“Critically, Saphineia engaged respectfully with our team, who felt Saphineia understood the challenges they face day-to-day and enabled them to better meet the expectations of our owners. Saphineia knows the Private Equity business and what our sponsors expected.”

CEO, Contract Manufacturer
Start the conversation

Ready to Strengthen Your Operations?

Whether you’re preparing for an exit, evaluating an acquisition, or looking to improve operations, we’d welcome a conversation.

Every conversation starts and ends with a food & beverage operator, never an account manager.